How to install our sandwich cement panel?

01 Alignment: Setting the base line of the installation position according the thickness of the wall panel.Then putting the panels to the corrected position.


02 Sawing wall panel: Using a professional installation size,in accordance with the proportion add water to turn into the pulpous state,using water brush wet for the wallboard of Waffle Blade,after applying in the groove of wallboard ,joint of floor and wallboard,joint of floor and beam column.


03Plastering the cement mortar: before fixing the wall panel,clearing the dust firstly and then plastering the cement mortar in concave and joints.


04 Fixing wall panels: before fixing wall panel,clearing the dust firstly and then plastering the cement mortar in concave and the joints


05 Calibrating:  after finishing to fix the wall panel,using teh crowbar to calibrate the right position.


06 Adjustments:after calibrating,sticking two steel bars to the wall panel to fix except the wood wedges( reinfore on bottom/top/left and right)


07 Filling joints:after the installation and adjustment,clearing the spilled mortar and using the steel to fill the joints with the depth4-5mm


08 Plastering the cement mortar: after installation for a week,taking out of the wood wedges and plastering the mortar on the joints.


09 Inserting the wires:It is forbidden to chisel the slot on the both sides of the same position.The distance should be more than 10cm between the switch and the box and the length of the pipeline can not be longer than 35cm.The depth of the slot can not exceed 2/3 of the thickness of the wall panel.


10 Installing the window and doors:we have many  different solutions for installing the windows and doors which include wood-doors,glass fire-resistant door.Aluminum alloy doors and window.etc.


Finally, you can click these links to check the installation video as follow:

0007         http://v.youku.com/v_show/id_XODE2MTQwNTEy.html


0003         http://v.youku.com/v_show/id_XODE1NjY3Nzg0.html


0008         http://v.youku.com/v_show/id_XODE2MTQ4NDg4.html


If you have any question about the panel installation,pld do let me know. My whatsapp:+8618649946842/email:sales03@zhongjingtai.com